TAXIWAYS RECONSTRUCTION PROJECT, Year 1 – Taxiways D, E, F, Q
PROJECT OVERVIEW
Description
In February 2025, work will commence on a $15.4 million, 6-month project to reconstruct segments of Taxiways D, E, F, and Q. This project will deliver important upgrades and extended lifespan to the airfield facilities that contribute to VNY’s world-class status. Improvements will be phased to maximize federal grant reimbursements and minimize operational impacts during construction.
Runway / Taxiway Closure Map and Height Restrictions
- Phase 1 and 2A (Estimated 2/11/25 to 4/17/25)
- Phase 2 and 3A (Estimated 4/17/25 to 5/20/25)
- Phase 3 and 3B (Estimated 5/20/25 to 6/26/25)
- Phase 4A and 4 (Estimated 6/26/25 to 7/31/25)
Information
Photo Gallery
Phase 1
- Week 1 (Week ending 2/14/25)
- Week 2 (Week ending 2/21/25)
- Week 3 (Week ending 2/28/25)
- Week 4 (Week ending 3/7/25)
- Week 5 (Week ending 3/14/25)
- Week 6 (Week ending 3/21/25)
- Week 7 (Week ending 3/28/25)
- Week 8 (Week ending 4/4/25)
- Week 9 (Week ending 4/11/25)
Phase 2
- Week 1 (Week ending 4/18/25)
- Week 2 (Week ending 4/25/25)
- Week 3 (Week ending 5/2/25)
- Week 4 (Week ending 5/9/25)
- Week 5 (Week ending 5/16/25)
Phase 3
- Week 1 (Week ending 5/23/25)
- Week 2 (Week ending 5/30/25)
- Week 3 (Week ending 6/6/25)
- Week 4 (Week ending 6/13/25)
- Week 5 (Week ending 6/20/25)
Phase 4
- Week 1 (Week ending 7/4/25)
- Week 2 (Week ending 7/11/25)
- Week 3 (Week ending 7/18/25)
- Week 4 (Week ending 7/25/25)